Five things to check before you fund a construction draw

By The Vaulted team · Published Nov 20, 2026 · 4 min read

Before releasing a draw, confirm the work is actually in place, compare it to what you've already paid, get the right lien waiver for the last payment, check the budget line it comes from, and write down why you approved it. Most draw losses come from skipping one of these, not from a bad borrower.

A rehab or construction loan is only as safe as its draws. The closing is usually fine: there's an appraisal, title, insurance and a budget everyone signed. The losses tend to come later, from a draw that paid for work that wasn't finished, or from a contractor who filed a lien after the lender had already paid the borrower for that work.

None of that takes a dishonest borrower. It takes a busy week and one skipped step. These are the five checks careful lenders run on every draw, in the order they usually run them.

1. Is the work actually in place?

A draw request is the borrower's description of the work. An inspection is someone else's. Before you fund, you want a recent inspection that says how far along the project is, ideally by line item, plus who inspected it and on what day. Photos from the borrower help, but they show what the borrower chose to photograph.

Pay attention to the date. An inspection from three weeks ago describes a different project than the one standing there today, in either direction.

2. Would this draw put you ahead of the work?

This is the check that matters most, and the arithmetic is simple. Work in place is the inspected percent complete times the rehab budget. Add up everything you've already funded, add this draw, and compare the two.

The rule: total funded, including this draw, stays at or below the work verified in place. If it doesn't, you're lending against work that doesn't exist yet.

Here's how it looks on a real file. The rehab budget is $80,000. You've funded $30,000 so far. The borrower asks for $12,000. The inspector reports the project 45% complete, which is $36,000 of work in place. Funding the full request would bring you to $42,000, or $6,000 ahead of the work. The careful answer is to fund $6,000 now and the rest after the next inspection shows it's done.

3. Did the last payment come with the right lien waiver?

A lien waiver is the contractor's signed statement giving up the right to file a lien for work they've been paid for. Before you release the next draw, you want the waiver for the money you already sent.

There are two kinds. A conditional waiver only takes effect once the contractor is actually paid, so it's the one that usually changes hands with a payment. An unconditional waiver is effective as soon as it's signed, so it's the one you want once the payment has cleared. California's contractor board puts it bluntly on its forms: an unconditional release is enforceable against the person who signs it even if they haven't been paid. Waiver forms and rules vary by state, and some states require specific wording, so ask your attorney which forms to use where you lend.

Also remember that a waiver from the general contractor doesn't cover subcontractors and suppliers who haven't been paid. On larger jobs, lenders ask for their waivers too.

4. Which budget line is this coming from?

Every draw should map to a line in the approved budget: demolition, roofing, kitchen, contingency. Three things are worth a second look. A request that doesn't match the work the inspector saw. A line that's already fully drawn. And contingency being used early in the project, which often means the budget was light from the start.

5. Write down why you approved it

Six months from now, someone may ask why this draw was paid: an investor in your fund, a buyer looking at the loan, or your attorney if the project goes sideways. The answer should already be on file: the inspection and its date, the percent complete, the lien waiver status, the amount approved, who approved it and when. A short note on anything unusual takes a minute and saves an argument later.

How Vaulted handles this

In Vaulted, every draw carries its own inspection record: the inspector, the day it was ordered and the day it was done, the percent complete and notes. Each draw also tracks its lien waiver as not received, conditional or unconditional. Draws are tied to the loan's budget categories, so you can see what each line was budgeted and what's been drawn against it. Borrowers send draw requests, with photos, through their portal.

Once an inspection's percent complete is recorded, Vaulted won't approve a draw above the work verified in place. There's no override: you approve less or record a newer inspection. In the example above, it would tell you to approve no more than $6,000. You can also set Vaulted to refuse any approval until an inspection is recorded, and to refuse the next draw while the previous one has no lien waiver.

Plans are $99, $149 and $199 a month, with a 30-day free trial and every feature unlocked during it. No card needed to start.

Whatever you use, run all five checks on every draw, including the small ones. The small draws are the ones that get waved through.

Questions

Do I need an inspection for every draw?

Most careful lenders inspect before every draw, because the inspection is what tells you the work is in place. Some waive it for very small draws, but that is exactly where funding ahead of the work tends to start.

Should I take a conditional or an unconditional lien waiver?

Usually a conditional waiver when the payment goes out, then an unconditional waiver for that payment once it has cleared, collected before you fund the next draw. Forms and requirements vary by state, so ask your attorney which ones to use.